File #: 21-202    Version: Name: Contract for the Nebraska Corridor Upgrade
Type: Contract Status: Approved
File created: 7/6/2021 In control: City Council
On agenda: 7/27/2021 Final action: 7/27/2021
Title: Communication from the City Manager and Director of Public Works with a Request to APPROVE the LOW BID of KNAPP CONCRETE CONTRACTORS, INC. in the Amount of $424,583.99, and Award a CONTRACT for the NEBRASKA CORRIDOR UPGRADE, with an Additional Authorization of $42,416.01 (10%) for Contingencies, for a Total Contract Award of $467,000.00. (Council District 3)
Attachments: 1. 21-202 Agreement.pdf, 2. Nebraska SubContUtStatement, 3. File Summary

ACTION REQUESTED: 

Title

Communication from the City Manager and Director of Public Works with a Request to APPROVE the LOW BID of KNAPP CONCRETE CONTRACTORS, INC. in the Amount of $424,583.99, and Award a CONTRACT for the NEBRASKA CORRIDOR UPGRADE, with an Additional Authorization of $42,416.01 (10%) for Contingencies, for a Total Contract Award of $467,000.00. (Council District 3)

Body

BACKGROUND: Nebraska Avenue is an important east-west corridor through the city. The portion of the roadway from Knoxville to Wisconsin runs through the East Bluff and provides vehicle and pedestrian access to the neighborhood. 

 

The proposed improvements include replacing deteriorated sidewalks and upgrading ADA sidewalk ramps.

 

Bids for the Nebraska Corridor Upgrade were advertised in the Peoria Journal Star and on the City’s website. Bids were opened on June 30, 2021, with two (2) bids received, as follows:

 

                     Contractor                                                                                                                              Total Bid                                          

Knapp Concrete Contractors                                                               $424,583.99                     

Otto Baum                                                                                                                              $499,286.23

 

Engineer’s Estimate:   $440,203.24

 

Staff recommends increasing the low bidder’s contract to $467,000.00 to accommodate a 10% contingency.

 

The Good Faith Efforts documentation submitted by Knapp Concrete Contractors was reviewed and approved. Knapp will be self-performing most of the work with one subcontractor (not a minority) for sodding.

 

Engineering for the Nebraska Corridor Upgrade was completed by Infrastructure Engineering, Inc.

 

FINANCIAL IMPACT: $217,000 will come from the 2021 approved budget intended for improvements to the corridor. In addition, $250,000 in Community Development Block Grant (CDBG) funds were previously approved (Item #21-062 on 3/9/2021) for added sidewalks and ADA ramps for this project. Construction must be complete by September 30, 2021, to utilize the CDBG funds. 

 

NEIGHBORHOOD CONCERNS: Sidewalks and ADA ramps in good condition are a benefit to the neighborhood.

                     

IMPACT IF APPROVED: The sidewalk and ramps will be reconstructed and the CBDG funds will be used.

 

IMPACT IF DENIED: The sidewalk and ramps will not be reconstructed. CBDG funds won’t be used for this project.

 

ALTERNATIVES: N/A

 

EEO CERTIFICATION NUMBER: 03566-211231

 

 

WHICH OF THE GOALS IDENTIFIED IN THE COUNCIL’S 2017 - 2032 STRATEGIC PLAN DOES THIS RECOMMENDATION ADVANCE?

 

1. Financially Sound City                     

2. Beautiful Peoria

 

WHICH CRITICAL SUCCESS FACTOR(S) FROM THE COMPREHENSIVE PLAN DOES THIS RECOMMENDATION IMPLEMENT?

 

1. Invest in our infrastructure and transportation.                     

2. Reinvest in neighborhoods.                     

 

DEPARTMENT: Public Works