File #: 23-034    Version: 1 Name: Prospect-Arcadia Traffic Calming
Type: Contract Status: Approved
File created: 1/24/2023 In control: City Council
On agenda: 2/14/2023 Final action: 2/14/2023
Title: Communication from the City Manager and Director of Public Works with a Request to APPROVE the LOW BID of OTTO BAUM, in the Amount of $167,600.00, for the PROSPECT-ARCADIA TRAFFIC CALMING, with an Additional Authorization of $ 16,760.00 (10%) for Contingencies, for a Total Contract Award of $ 184,360.00. (Council District 3)
Attachments: 1. 23-034 signed

ACTION REQUESTED: 

Title

Communication from the City Manager and Director of Public Works with a Request to APPROVE the LOW BID of OTTO BAUM, in the Amount of $167,600.00, for the PROSPECT-ARCADIA TRAFFIC CALMING, with an Additional Authorization of $ 16,760.00 (10%) for Contingencies, for a Total Contract Award of $ 184,360.00. (Council District 3)

 

Body

BACKGROUND:  Prospect Road is a five-lane arterial roadway through the City of Peoria. The existing pedestrian crossing on the north side of Arcadia connects to Glen Oak Park and a bus stop. The City has been made aware of many near misses as pedestrians try to cross Prospect.

 

After reviewing the project area, City staff determined this would be a good location to narrow the roadway with bump-outs on the west side of Prospect. In addition, the center turn lane provides room to allow pedestrians to cross the street in two movements. Because a traffic study had been completed, the City was able to utilize Federal Transit Authority (FTA) 5310 funds that could no longer be utilized for a pedestrian improvement along War Memorial Drive.

 

Working with Tri-County Regional Planning Commission, the City got the funds reprogrammed for the Prospect-Arcadia project. The FTA funds will pay for 80% of the project up to $96,000.

 

The plans and specifications were prepared by Hanson Professional Services Inc. The Advertisement for Bids for this project was published in the Peoria Journal Star and on the City’s website. Public Works opened Bids on January 26, 2023, with 3 bids received.

 

Contractor                                                               Total Bid

C&G Concrete                                          $180,614.00

Otto Baum                                                               $167,600.00

ICCI                                                                                    $214,631.49

 

Engineer’s Estimate                                           $178,840.00

 

Otto Baum is a local business that has successfully performed work for the city in the past.

 

The subcontractor utilization statement submitted by the Otto Baum proposes that the company will be utilizing the following

                     MBE subcontractor: Millennia Professional Services for testing and construction layout 6.33% of the total contract amount, Buddy’s Ground Maintenance for Sodding 2.52% of the contract amount, and Lizz Trucking for trucking 1.75% of the contract amount for a total of 10.60%. The City’s MBE goal is 10%.

                     WBE subcontractor: JD Traffic for traffic control 1.94% of the total contract amount and Kelley Ironworks for handrail 3.26% of the total contract amount, for a total of 5.20%. The City’s WBE goal is 5%.

 

On a past Folkers Ave. project, the contractor’s minority and female workforce utilizations were 26.99% minority (28% goal) and 7.18% women (3% goal).

 

Documentation was reviewed and approved by the Chief Diversity and Inclusion Officer.

 

 

FINANCIAL IMPACT:  The project is 80% funded up to $96,000 through the FTA. The remaining amount is funded through the Community Investment Plan Sidewalks and ADA Ramps Project, Project Number S2301, and Neighborhood Traffic Calming, Project Number R2306.

 

NEIGHBORHOOD CONCERNS:  Citizens have expressed safety concerns crossing at this location. Cars are speeding and the crossing distance is long.

                     

IMPACT IF APPROVED: The project will be awarded and constructed in 2023.

 

IMPACT IF DENIED: The project will not be constructed, and the FTA funds will be returned.

 

ALTERNATIVES:  None.

 

EEO CERTIFICATION NUMBER: 00073-240331

 

WHICH OF THE GOALS IDENTIFIED IN THE COUNCIL’S 2017 - 2032 STRATEGIC PLAN DOES THIS RECOMMENDATION ADVANCE?

 

1. Safe Peoria                     

2. Financially Sound City

3. Beautiful Peoria

 

WHICH CRITICAL SUCCESS FACTOR(S) FROM THE COMPREHENSIVE PLAN DOES THIS RECOMMENDATION IMPLEMENT?

 

1. Invest in our infrastructure and transportation.                     

2. Reinvest in neighborhoods.                     

3. Support sustainability.                     

 

DEPARTMENT: Public Works