Title: Communication from the City Manager and the Director of Public Works with a REQUEST to ADOPT an ORDINANCE Authorizing the City Manager to ACQUIRE REAL ESTATE for RIGHT-OF-WAY or PERMANENT EASEMENT Purposes, in an Amount Not to Exceed $15,000.00 Per Parcel for 2014; with Subsequent Year Totals Not to Exceed the Annual Budgeted Amount. (Also Refer to Ord. No. 16,979) [City Wide]
Indexes: Goal 1 - Financially Sound City , Goal 3 - Beautiful Peoria, Have an efficient government., Invest in our infrastructure and transportation, Support sustainability
Attachments: 1. ORD NO 17,169, 2. An Ordinance Auth CM to Acquire ROW Property NTE $15000
ACTION REQUESTED:  
Title
Communication from the City Manager and the Director of Public Works with a REQUEST to ADOPT an ORDINANCE Authorizing the City Manager to ACQUIRE REAL ESTATE for RIGHT-OF-WAY or PERMANENT EASEMENT Purposes, in an Amount Not to Exceed $15,000.00 Per Parcel for 2014; with Subsequent Year Totals Not to Exceed the Annual Budgeted Amount. (Also Refer to Ord. No. 16,979) [City Wide]
 
Body
BACKGROUND:  Currently, there are fifty-one (51) parcels being appraised and their purchases being negotiated for the University Avenue (Nebraska Avenue to War Memorial Drive) Improvement Project.  Under Item #14-293, the City purchased the first of the 51 Parcels. That initial purchase included the largest parcel of property for the Project. Each of the other 50 parcels would need individual approval by City Council to complete their purchases.  The attached, proposed Ordinance would authorize the City Manager to accomplish this task more efficiently, for all projects, through direction to Staff and professional engineering staff under contract with the City. Most projects are time-sensitive, requiring completion of right of way acquisition before a project may be advertised for competitive bid in short construction seasons.
 
FINANCIAL IMPACT:  ROW purchase payments will be paid annually through budgeted project funds.
 
NEIGHBORHOOD CONCERNS:  The ROW acquisition provides Public Land needed to build improvement projects.  
      
IMPACT IF APPROVED:  Staff can continue to implement projects with timely right of way acquisition being cleared prior to the competitive bid process.
 
IMPACT IF DENIED:   Projects may not be cleared for bidding in a timely manner, sometimes jeopardizing state and federal funding during short construction seasons.
 
ALTERNATIVES:   As Council Directs.
 
EEO CERTIFICATION NUMBER: N/A
 
WHICH OF THE GOALS IDENTIFIED IN THE COUNCIL'S 2014 - 2029 STRATEGIC PLAN DOES THIS RECOMMENDATION ADVANCE?
 
1. Financially Sound City Government, Effective City Organization      
2. Attractive Neighborhoods with Character: Safe and Livable
 
WHICH CRITICAL SUCCESS FACTOR(S) FROM THE COMPREHENSIVE PLAN DOES THIS RECOMMENDATION IMPLEMENT?
 
1. Invest in our infrastructure and transportation.      
2. Support sustainability.      
3. Have an efficient government.      
 
DEPARTMENT: Public Works