ACTION REQUESTED:
Title
Communication from the City Manager and Director of Public Works with a Request to APPROVE an AGREEMENT to Pay FRONTIER COMMUNICATIONS in the Amount of $55,208.00 for the Relocation of Existing Fiber Optic Cables for the Construction of the Alta Lane and Radnor Road Roundabout Project. [Council District 5]
Body
BACKGROUND: Frontier Communications has existing fiber optic cables located in private easements along the south side of Alta Lane’s alignment. These easements were in place before the City acquired the ROW for the proposed Alta/Radnor Roundabout project; therefore, the City must compensate Frontier Communications for the relocation of the existing cables. An agreement with Frontier Communications is attached.
FINANCIAL IMPACT: The total of $55,208.00 will be paid to Frontier Communications from Project E06015 (Alta-Radnor Roundabout).
NEIGHBORHOOD CONCERNS: This project will allow better access to this portion of the City.
IMPACT IF APPROVED: The utility will relocate the cables for the Alta Lane & Radnor Road Roundabout Project.
IMPACT IF DENIED: The Council would need to provide further direction to Staff.
ALTERNATIVES: As Council directs.
EEO CERTIFICATION NUMBER: N/A
WHICH OF THE GOALS IDENTIFIED IN THE COUNCIL’S 2014 - 2029 STRATEGIC PLAN DOES THIS RECOMMENDATION ADVANCE?
1. Grow Peoria: Businesses, Jobs, and Population
2. Financially Sound City Government, Effective City Organization
WHICH CRITICAL SUCCESS FACTOR(S) FROM THE COMPREHENSIVE PLAN DOES THIS RECOMMENDATION IMPLEMENT?
1. Invest in our infrastructure and transportation.
2. Reinvest in neighborhoods.
DEPARTMENT: Public Works