File #: 23-135    Version: 1 Name: Culvert Improvements - Dry Run Creek at Glen and Sheridan
Type: Contract Status: Approved
File created: 3/28/2023 In control: City Council
On agenda: 4/25/2023 Final action: 4/25/2023
Title: Communication from the City Manager and Director of Public Works with a Request to APPROVE the LOW BID of J.C. DILLON, INC. in the Amount of $494,340.00 for the CULVERT REPLACEMENT TRIBUTARY C UNDER GLEN AVENUE, with an Additional Authorization of $49,460.00 (10%) for Contingencies, for a Total Contract Award of $ 543,800.00. (Council District 3)
Attachments: 1. Glen Culvert, 2. agmt 23-135
ACTION REQUESTED:
Title
Communication from the City Manager and Director of Public Works with a Request to APPROVE the LOW BID of J.C. DILLON, INC. in the Amount of $494,340.00 for the CULVERT REPLACEMENT TRIBUTARY C UNDER GLEN AVENUE, with an Additional Authorization of $49,460.00 (10%) for Contingencies, for a Total Contract Award of $ 543,800.00. (Council District 3)

Body
BACKGROUND: Inspections of storm sewers and culverts identified the culvert segment under Glen Avenue near the Red Carpet Car Wash and Spotted Cow Restaurant to be in poor condition. This project will replace the 5-foot wide by 6-foot tall culvert under Glen Avenue that ties into the recently relocated 6-foot diameter culvert near the Red Carpet Car Wash Property. The culvert being replaced under Glen Avenue was originally built in the 1930s.

The plans and specifications were prepared by Crawford, Murphy & Tilly (CMT). The Advertisement for Bids for this project was published in the Peoria Journal Star and on the City's website. Public Works opened Bids on March 23, 2023, with three bids received.

Contractor Total Bid
J.C. Dillon Inc. $ 494,300.00
Stark Excavating, Inc $ 956,316.00
Knapp Concrete Contractors, Inc $1,035,115.00

Engineer's Estimate $ 477,225.00

J.C. Dillon, Inc. is a local business that has successfully performed work for the city in the past.

The subcontractor utilization statement submitted by J.C. Dillon proposes that the company will be utilizing the following:
* MBE subcontractor: Kerry Brown Trucking for trucking 5.75% of the total contract amount The City's MBE goal is 10%.
* WBE subcontractor: JD Traffic for Traffic Control 4.43% of the total contract amount The City's WBE goal is 5%.

On a past project STORM DRAINAGE REPAIR ANNUAL CONTRACT 2022, the contractor's minority and female workforce utilizations were 29.60% minority (18% goal) and 0% women (3% goal).

Documentation was reviewed and approved by the Chief Diversity and Inclusion Of...