File #: 21-262    Version: 1 Name: HMA Overlay Contract - 2021
Type: Contract Status: Approved
File created: 9/1/2021 In control: City Council
On agenda: 9/14/2021 Final action: 9/14/2021
Title: Communication from the City Manager and Director of Public Works with a Request to APPROVE the Low BID of R. A. CULLINAN & SONS, and APPROVE a Construction CONTRACT, in an Amount Not to Exceed $900,000.00, from the Base Bid of $749,719.92, for the HMA OVERLAY CONTRACT - 2021. (Council Districts 3, 4, and 5)
Attachments: 1. 21-262 Signed Agreement
ACTION REQUESTED:
Title
Communication from the City Manager and Director of Public Works with a Request to APPROVE the Low BID of R. A. CULLINAN & SONS, and APPROVE a Construction CONTRACT, in an Amount Not to Exceed $900,000.00, from the Base Bid of $749,719.92, for the HMA OVERLAY CONTRACT - 2021. (Council Districts 3, 4, and 5)
Body
BACKGROUND: Public Works reviewed the condition of local streets throughout the city and identified five local streets to mill and overlay. The streets include High Point Terrace (District 3), Glen Ave. and Austin Dr. (District 4), and Altorfer Dr. and Sommer St. (District 5).

Public Works prepared the contract specifications, and bids were received on August 26, 2021 with one bid received, as follows:

Contractor Total Bid
R.A. Cullinan (UCM) $749,719.92

Engineer's base estimate: $829,813.55

Since the time of our bid opening for this project, staff identified Nebraska Ave. as an additional street to add to the contract. In order to address Nebraska, staff recommends increasing this project to $900,000.00, which is within our original CIP budget.

R.A. Cullinan is a local business that has successfully performed work for the City in the past. Most comparably to this project, they performed the 2019 Sheridan Road Mill & Overlay Project. They achieved 14.7% (18% goal) hours performed by Minority workers and 6.3% (3% goal) of hours performed by Female workers, per eprismsoft.com.

The Good Faith Efforts documentation submitted by R.A. Cullinan were reviewed and approved by Public Works. The Company proposes to utilize 0.9% MBEs for Trucking and 1.3% WBEs for Traffic Control and Trucking. Due to the nature of the project, there are minimal opportunities for subcontractors based on the limited scope of work that requires specialized construction equipment. Furthermore, the Contractor will make a good faith effort to reach and exceed the 18% minority utiliz...

Click here for full text