Title: Communication from the City Manager and Director of Public Works with a Request to ACCEPT the LOW BID of R.A. CULLINAN & SON, INC., a Division of UNITED CONTRACTORS MIDWEST, and Award a Construction CONTRACT, in the Amount of $549,344.50, for the Base Bid Plus 10% Contingency for the SEAL-COATING CONTRACT - 2021. (All Council Districts)
Attachments: 1. 21-200 Seal Coating Contract
ACTION REQUESTED:
Title
Communication from the City Manager and Director of Public Works with a Request to ACCEPT the LOW BID of R.A. CULLINAN & SON, INC., a Division of UNITED CONTRACTORS MIDWEST, and Award a Construction CONTRACT, in the Amount of $549,344.50, for the Base Bid Plus 10% Contingency for the SEAL-COATING CONTRACT - 2021. (All Council Districts)

Body
BACKGROUND Public Works proposes to continue the annual seal-coating contract to preserve roads in good condition to prolong their lifespan and delay costly major reconstruction projects. Sealcoating is a surface treatment used to extend the life of pavement in which the pavement is sprayed with asphalt, which is immediately covered with aggregate and rolled. Seal coats are primarily used to seal pavement with non-load associated cracks and to improve surface friction. This contract will also cover various asphalt work that needs to be completed in preparation for the seal coat.

Public Works prepared the contract specifications and advertised for bids. Bids were received and opened on June 28, 2021, with one bidder submitting. There are not many contractors in this area that perform this type of specialized work. (Attached is a list of the streets to be treated in the 2021 Program.)

Contractor
Base Bid Amount
R.A. Cullinan & Son, Inc., a Division of UCM
$499,404.10

RA Cullinan/UCM is a local contractor that has successfully performed numerous construction projects in the past for the City.

The Good Faith Efforts documentation submitted by R.A. Cullinan & Son, A Division of UCM, has been reviewed and approved. Due to the specialized nature of this work, subcontracting opportunities are limited, however R.A. Cullinan aims to meet City minority participation goals. In 2019 the company exceeded the City's minority workforce goal of 18% and exceeded the City's female workforce goal of 3%. R.A. Cullinan is committed to meeting the goals in 2021.

FINANCIAL IMPACT: Funding is available thr...