ACTION REQUESTED:
Title
Communication from the City Manager and Public Works Director with a Request to APPROVE the Following for VARIOUS ENGINEERING SERVICES:
A. The Second Amendment to the MASTER PROFESSIONAL SERVICES AGREEMENT with AKRF, INC., in an Amount Not to Exceed $325,000.00; and,
B. The Second Amendment to the MASTER PROFESSIONAL SERVICES AGREEMENT with CRAWFORD, MURPHY & TILLY, in an Amount Not to Exceed $650,000.00; and,
C. The Third Amendment to the MASTER PROFESSIONAL SERVICES AGREEMENT with FOTH INFRASTRUCTURE & ENVIRONMENT, LLC, in an Amount Not to Exceed $250,000.00; and,
D. The Second Amendment to the MASTER PROFESSIONAL SERVICES AGREEMENT with HANSON PROFESSIONAL SERVICES, INC., in an Amount Not to Exceed $2,100,000.00; and,
E. The Second Amendment to the MASTER PROFESSIONAL SERVICES AGREEMENT with HUTCHISON ENGINEERING, INC., in an Amount Not to Exceed $150,000.00; and,
F. The Second Amendment to the MASTER PROFESSIONAL SERVICES AGREEMENT with MAURER-STUTZ, INC., in an Amount Not to Exceed $150,000.00; and,
G. The Second Amendment to the MASTER PROFESSIONAL SERVICES AGREEMENT with MIDWEST ENGINEERING ASSOCIATES, INC., in an Amount Not to Exceed $1,150,000.00; and,
H. The Second Amendment to the MASTER PROFESSIONAL SERVICES AGREEMENT with MILLENNIA PROFESSIONAL SERVICES OF ILLINOIS, LTD, in an Amount Not to Exceed $250,000.00; and,
I. The Second Amendment to the MASTER PROFESSIONAL SERVICES AGREEMENT with TERRA ENGINEERING, LTD., in an Amount Not to Exceed $1,000,000.00.
Body
BACKGROUND: On December 22, 2018, Council approved Master Services Agreement (Item No. 18-369) with nineteen consultants. These agreements originally were to last until December 31, 2021. In 2021, Public Works extended the Master Service Agreements (MSA) with these consultants for one year, through December 31, 2022 (Item No. 21-101). The consultant agreed to hold their prices in 2022 to the 2021 rates.
Public Works reviewed the Community Investment Plan ...