File #: 15-266    Version: 1 Name: ADA Ramps 2015 Contract
Type: Contract Status: Approved
File created: 7/27/2015 In control: City Council
On agenda: 8/11/2015 Final action: 8/11/2015
Title: Communication from the City Manager and Director of Public Works with a Request to Accept the LOW BID of ILLINOIS CIVIL CONTRACTORS, INC. and AWARD the CONSTRUCTION CONTRACT for the ADA RAMP INSTALLATION/REPLACEMENT PROGRAM - 2015, in a Not-to-Exceed Amount of $157,748.92. (City-Wide)
Indexes: Goal 1 - Financially Sound City , Goal 3 - Beautiful Peoria, Invest in our infrastructure and transportation, Reinvest in neighborhoods, Support sustainability
Attachments: 1. 15-266 Agmt Illinois Civil Contractors, Inc., 2. 2015 ADA Ramps Map
ACTION REQUESTED:
Title
Communication from the City Manager and Director of Public Works with a Request to Accept the LOW BID of ILLINOIS CIVIL CONTRACTORS, INC. and AWARD the CONSTRUCTION CONTRACT for the ADA RAMP INSTALLATION/REPLACEMENT PROGRAM - 2015, in a Not-to-Exceed Amount of $157,748.92. (City-Wide)

Body
BACKGROUND: The ADA Ramp Reconstruction Project will continue to implement the City's approved ADA Transition Plan. Work in 2015 will focus on sidewalk and ADA curb ramp replacement to bring intersection quadrants up to ADA compliance.

Citizen requests for ADA Ramp repairs have risen sharply. Project locations are noted on the attached map. Sites that have had recent trip complaints are included.

The project was advertised on July 8th and 9th with bids opened on July 29nd with two bids received as follows:

Contractor Total Bid
Illinois Civil Contractors, Inc. $185,584.00
P.A. Atherton, Construction, Inc. $187,612.00

Engineer's base estimate: $170,309.00

The contract price will be reduced to $157,748.92 to stay within the project budget. The attached 2015 ADA Ramps Map shows locations of planned ADA Ramp upgrades within budget of Construction.

Illinois Civil Contractors, Inc. (ICCI) is a local business that has successfully performed work for the City in the past. This contractor also worked on the City's 2012, 2013, and 2014 ADA Ramp contracts.

The Good Faith Efforts documentation submitted by ICCI has been reviewed and approved by the Equal Opportunity Manager. The company will subcontract with a Minority Business Enterprise (MBE) to provide services equal to 4.0% of the contract and with a Women Business Enterprise (WBE) to provide services equal to 1.4% of the contract.

Mohr & Kerr Engineering & Land Surveying will be performing Engineering services through their Master Engineering Services Agreement Extension with the City, which Council approved on December 9, 2014.


FINANCIAL IMPACT: Th...