File #: 17-230    Version: 1 Name: Western Ave Suppl MFT Reso & TERRA Agr
Type: Resolution Status: Approved
File created: 7/12/2017 In control: City Council
On agenda: 7/25/2017 Final action: 7/25/2017
Title: Communication from City Manager and Director of Public Works with a Request for the Following: A. APPROVE the SUPPLEMENTAL STATE MOTOR FUEL TAX RESOLUTION, in the Amount of $1,230,000.00, for Preliminary Engineering and Right-of-Way Services for the WESTERN AVENUE PROJECT (ADAMS STREET to LINCOLN AVENUE); and B. APPROVE SUPPLEMENT #1 to the Preliminary Engineering AGREEMENT with TERRA ENGINEERING, LTD, in the not-to-exceed Amount of $1,214,621.18 for the Project. (Council District 1)
Indexes: Goal 1 - Financially Sound City , Goal 2 - Safe Peoria, Goal 3 - Beautiful Peoria, Invest in our infrastructure and transportation, Reinvest in neighborhoods, Support sustainability
Attachments: 1. AGMT NO. 17-230 Terra Engineering Preliminary Agmt, 2. AGMT NO. 17-230 Terra Engineering Supplement #1, 3. MFT RES NO 17-230 WESTERN AVE PROJ, 4. Western MFT Suppl Reso 2017 NEW, 5. 7-25-17 CC Replacement Western Supp Agreement, final, 6. Western Location Map, 7. TERRA ENG CERT_2017-2018_City of Peoria EEO
Related files: 21-149, 21-148
ACTION REQUESTED:
Title
Communication from City Manager and Director of Public Works with a Request for the Following:

A. APPROVE the SUPPLEMENTAL STATE MOTOR FUEL TAX RESOLUTION, in the Amount of $1,230,000.00, for Preliminary Engineering and Right-of-Way Services for the WESTERN AVENUE PROJECT (ADAMS STREET to LINCOLN AVENUE); and

B. APPROVE SUPPLEMENT #1 to the Preliminary Engineering AGREEMENT with TERRA ENGINEERING, LTD, in the not-to-exceed Amount of $1,214,621.18 for the Project. (Council District 1)

Body
BACKGROUND: Western Avenue, between Adams Street and Lincoln Avenue, is in need of improvements. This roadway is also in the combined sewer area. This project will be designed as a "Complete, Green Street" accommodating all users of the right-of-way and incorporating storm water management features to abate combined sewer overflows. The project will maximize co-benefits for the community by following the approach developed by the i-Team.

In 2016, $150,000 in MFT funds were used to begin engineering for this project. (Ref. Council Item #16-220). We are now ready to complete preparation of construction plans and right of way acquisition. A location map and the Supplemental Motor Fuel Tax Resolution (for preliminary engineering services and city staff time involving the design of the replacement of curb and gutter, sidewalk, storm water management systems, lighting systems, and pavement improvements along Western, as well as right of way acquisition), are attached to this communication.

TERRA Engineering Ltd. will be providing the design engineering services on this project under a work order from its Master Services Agreement approved by Council April 12, 2016 (Item #16-119-A). TERRA Engineering Ltd. is a DBE. The Illinois Department of Transportation requires an Engineering Agreement in an IDOT format to approve the use of the MFT funds for the work. This agreement is also attached.

The cost of the roadway project is estimated at $10 milli...

Click here for full text