File #: 19-238    Version: 1 Name: Harrison Impact Zone 2019 Project Award
Type: Contract Status: Approved
File created: 7/11/2019 In control: City Council
On agenda: 7/23/2019 Final action: 7/23/2019
Title: Communication from the City Manager and Interim Director of Public Works with a Request to ACCEPT the LOW BID of C&G CONCRETE CONSTRUCTION CO., in the Amount of $81,734.00, and Award a CONTRACT for the HARRISON IMPACT ZONE 2019 PROJECT, with an Additional Authorization of $8,266.00, for a Total Contract Award of $90,000.00. (Council District 1)
Indexes: Goal 1 - Financially Sound City , Goal 3 - Beautiful Peoria, Have an efficient government., Invest in our infrastructure and transportation, Reinvest in neighborhoods
Attachments: 1. AMGT NO 19-238 (C&G Concrete Construction), 2. Harrison Impact Zone Sidewalks

ACTION REQUESTED: 

Title

Communication from the City Manager and Interim Director of Public Works with a Request to ACCEPT the LOW BID of C&G CONCRETE CONSTRUCTION CO., in the Amount of $81,734.00, and Award a CONTRACT for the HARRISON IMPACT ZONE 2019 PROJECT, with an Additional Authorization of $8,266.00, for a Total Contract Award of $90,000.00. (Council District 1)

 

Body

BACKGROUND:  In 2018, the CDBG funding was not available in a timely sense to perform construction. Since then, the CDBG funds have become available through Community Development Department’s coordination with HUD.   

 

This will be the final year of Harrison Impact Zone infrastructure work per the Community Investment Plan. The focus of the 2019 work will be on sidewalk improvements on the south side of W Montana St, from Oregon St to Ligonier St. This project will also improve the sidewalk on the east side of Idaho St, from Trewyn Avenue to Montana Street.

 

HUD grant funding for Community Development Block Grants was approved for usage as of June 27, 2019. Hence, this contract was subsequently advertised for bids. The grant funds are to be expended by October 31, 2019.

 

The Harrison Impact Zone 2019 project was advertised, and bids were opened on July 12, 2019 with three bids received, as follows:

 

                                          Contractor                                                                                                           Total Bid

                     C&G Concrete                                                                                                         $81,734.00                     

                     Illinois Civil Contractors, Inc.                                                                                     $96,777.00

Knapp Concrete                                                                                                         $115,561.50

 

Engineer’s base estimate:   $88,814.00

 

Staff recommends authorizing this construction contract being increased above the bid amount to $90,000.

 

C&G Concrete is a local business that has worked for the City on several recent projects such as 2016’s Manor Parkway and 2018’s Warehouse District Sidewalks. They performed the Warehouse District Sidewalks project in late 2018 with 18.10% of hours performed by Minority workers.

 

The Good Faith Efforts documentation submitted by C&G Concrete has been reviewed and approved. C&G Concrete is a Women Business Enterprise and will perform the limited amount of work themselves. They will make a good faith effort to reach the 18% minority workforce hours and 3% female workforce hours’ goals.

 

Engineering for the Harrison Impact Zone program will be completed by Public Works Staff.

 

FINANCIAL IMPACT:  The total budget for this reconstruction project will be funded from the Community Investment Plan’s Harrison Impact Zone 2018 Project PB1809/S1807.  Contract work for $90,000 is proposed, and the remaining $10,000.00 will be for staff time on the grant administration, project bidding, and construction observation. The full $100,000 is funded through the Community Development Block Grant.

 

NEIGHBORHOOD CONCERNS:  Sidewalk improvements will benefit neighborhood residents.   

                     

IMPACT IF APPROVED:  Sidewalks in the area will be upgraded and the Community Development Block Grant will be utilized.  

 

IMPACT IF DENIED:  The project would be delayed, and the Community Development Block Grant may omit this project from its authorized funding.

 

ALTERNATIVES:  As Council Directs.

 

EEO CERTIFICATION NUMBER: C&G Concrete has current EEO Certification #00129-191231.

 

WHICH OF THE GOALS IDENTIFIED IN THE COUNCIL’S 2017 - 2032 STRATEGIC PLAN DOES THIS RECOMMENDATION ADVANCE?

 

1. Safe Peoria                     

2. Financially Sound City

 

WHICH CRITICAL SUCCESS FACTOR(S) FROM THE COMPREHENSIVE PLAN DOES THIS RECOMMENDATION IMPLEMENT?

 

1. Invest in our infrastructure and transportation.                     

2. Reinvest in neighborhoods.                     

3. Improve District 150.                     

 

DEPARTMENT: Public Works