File #: 20-212    Version: 1 Name: NORTH VALLEY TIF SIDEWALK IMPROVEMENTS
Type: Contract Status: Approved
File created: 8/12/2020 In control: City Council
On agenda: 8/25/2020 Final action: 8/25/2020
Title: Communication from the City Manager and Director of Public Works with a Request to APPROVE the LOW BID of HOROWITZ CONCRETE CO., in the Amount of $296,745.00, and Award a CONTRACT for the NORTHSIDE BUSINESS PARK TIF SIDEWALK IMPROVEMENTS, with an Additional Authorization of $14,837.25 (5%) for Contingencies, for a Total Contract Award of $311,582.25. (Council District 1)
Indexes: Goal 1 - Financially Sound City , Goal 2 - Safe Peoria, Goal 3 - Beautiful Peoria, Have an efficient government., Invest in our infrastructure and transportation, Reinvest in neighborhoods
Attachments: 1. Northside Business Park TIF map, 2. Northside Business Park TIF 2020-2021 Budget, 3. 20-212
ACTION REQUESTED:
Title
Communication from the City Manager and Director of Public Works with a Request to APPROVE the LOW BID of HOROWITZ CONCRETE CO., in the Amount of $296,745.00, and Award a CONTRACT for the NORTHSIDE BUSINESS PARK TIF SIDEWALK IMPROVEMENTS, with an Additional Authorization of $14,837.25 (5%) for Contingencies, for a Total Contract Award of $311,582.25. (Council District 1)
Body
BACKGROUND: The Northside Business Park TIF provides funding for public infrastructure improvements within the TIF District. See attached map and budget sheet. The Northside Business Park TIF will expire in 2022.

The 2020 approved budget has $700,000 intended for sidewalk and infrastructure improvements in this TIF District. Staff requests the approval to spend $490,182.25 of the $700,000 for this current project (see expenditure breakdown below).

The subject sidewalk contract provides for replacement and infill sidewalk along City streets in the TIF district. This contract will be the first of two for this work. The second contract is intended to replace sidewalk ramps at the intersections with City streets and Jefferson Street or Adams Street and must include IDOT approvals and permits.

Engineering for the sidewalk work has been initiated by Farnsworth Group for both contracts, and for additional design work on Spring Street as part of the conclusion of the TIF.


Bids for the North Valley TIF Sidewalk Improvements were advertised in the Peoria Journal Star and on the City's website. Bids were opened on August 6, 2020 with four (4) bids received, as follows:

Contractor Total Bid
Horowitz Concrete Co. $296,745.00
C & G Concrete Company, Inc. $299,630.50
Illinois Civil Contractors, Inc. $308,572.00
Otto Baum $367,694.64

Engineer's Estimate: $350,000.00

Staff recommends increasing the low bidder's contract to $311,582.25 to accommodate a 5% contingency.

The Good Faith Efforts documentation su...

Click here for full text