File #: 21-093    Version: 1 Name: Sign Installation - IDOT Agreement JN-421-014 Contract 68G21 Signal Modernization
Type: Agreement Status: Approved
File created: 3/19/2021 In control: City Council
On agenda: 4/13/2021 Final action: 4/13/2021
Title: Communication from the City Manager and Director of Public Works with a Request to APPROVE and Direct the City Manager to Execute an AGREEMENT with the ILLINOIS DEPARTMENT OF TRANSPORTATION (IDOT), in the Amount of $11,213.00, Plus Contingency, for the City's Participation in MODERNIZING TRAFFIC SIGNALS on US 116 (MACARTHUR HIGHWAY & WASHINGTON STREET, IL 29 (ADAMS STREET) & SPRING STREET, IL 29 (JEFFERSON STREET) & SPRING STREET, IL 40 (KUMPF BOULEVARD) & MONROE/GARRETT and US 150 (WAR MEMORIAL DRIVE) & PROSPECT. (Council Districts 1 & 3)
Attachments: 1. 68G21 Agreement, 2. 68G21 Plans, 3. 68G21 Letter, 4. 21-093 AGREEMENT.pdf, 5. 21-093 AGREEMENT MAPS.pdf
ACTION REQUESTED:
Title
Communication from the City Manager and Director of Public Works with a Request to APPROVE and Direct the City Manager to Execute an AGREEMENT with the ILLINOIS DEPARTMENT OF TRANSPORTATION (IDOT), in the Amount of $11,213.00, Plus Contingency, for the City's Participation in MODERNIZING TRAFFIC SIGNALS on US 116 (MACARTHUR HIGHWAY & WASHINGTON STREET, IL 29 (ADAMS STREET) & SPRING STREET, IL 29 (JEFFERSON STREET) & SPRING STREET, IL 40 (KUMPF BOULEVARD) & MONROE/GARRETT and US 150 (WAR MEMORIAL DRIVE) & PROSPECT. (Council Districts 1 & 3)

Body
BACKGROUND:
The State (IDOT), in order to facilitate the free flow of traffic and ensure safety to the motoring and pedestrian public, is desirous of modernizing traffic signals by installing new traffic signal cabinets and controllers, communication equipment, video detection systems, and by performing all other work necessary to complete the improvement in accordance with the approved plans and specifications. The City is desirous of the improvements which will be an immediate, permanent benefit to the motoring and pedestrian public.

The State (IDOT) has agreed to make the surveys, prepare plans and specifications, receive bids and award the contract, furnish engineering inspection during construction and cause the improvement to be built in accordance with plans, specifications and contract. IDOT has also agreed to pay for all construction and engineering costs, subject to reimbursement by the City, as stipulated.

The City will provide partial funding for this project. Please note that all costs are estimated. The City will be responsible for actual costs of the constructed items, except for traffic signal amounts, which may total up to 125% of the estimated amount.

Traffic signal improvements will be made at the Joint City/State owned traffic signals at US 116 (MacArthur Hwy. & Washington St., IL 29 (Adams St.) & Spring St., IL 29 (Jefferson St.) & Spring St., IL 40 (Kumpf Blvd.) & Mon...

Click here for full text