File #: 22-112    Version: 1 Name: Buckthorn Way Reconstruction
Type: Contract Status: Approved
File created: 3/21/2022 In control: City Council
On agenda: 4/12/2022 Final action: 4/12/2022
Title: Communication from the City Manager and Director of Public Works with a Request to ACCEPT the LOW BID of ILLINOIS CIVIL CONTRACTORS, INC., in the Amount of $273,047.00, and APPROVE a CONTRACT for the BUCKTHORN WAY RECONSTRUCTION, with an Additional Authorization of $27,304.70 (10%) for Contingencies, for a Total Award of $300,051.70. (Council District 5)
Attachments: 1. Buckthorn, 2. 22-112 Signed Contract_0001
ACTION REQUESTED:
Title
Communication from the City Manager and Director of Public Works with a Request to ACCEPT the LOW BID of ILLINOIS CIVIL CONTRACTORS, INC., in the Amount of $273,047.00, and APPROVE a CONTRACT for the BUCKTHORN WAY RECONSTRUCTION, with an Additional Authorization of $27,304.70 (10%) for Contingencies, for a Total Award of $300,051.70. (Council District 5)

Body
BACKGROUND: Buckthorn Way is a residential street in dire need of reconstruction due to poor road condition, with a Pavement Condition Index (PCI) of 38. This project is a one-block concrete roadway reconstruction project. The project also includes a complete streets concept with new sidewalks, ADA ramps and curb and gutter. Construction is schedule to be complete by August 12, 2022.

Hermann & Associates, LLC prepared the plans and specifications. Public Works received bids on March 22, 2022, with five bidders submitting.

The results are shown below:

Contractor
Total Bid


Illinois Civil Contractors
$273,047.00
Otto Baum
$302,704.58
Stark Excavating
$340,407.45
Knapp Concrete
$346,334.00
RA Cullinan
$348,537.43

The Engineer's estimate for the project is $440,055.00

Illinois Civil Contractors (ICCI) is a local business that has successfully performed work for the City many times in the past.

The subcontractor utilization statement submitted by prime contractor Illinois Civil Contractors Inc., demonstrates that the company will be utilizing the following WBE subcontractors: CJL Landscaping for top soil and sodding services equaling 4% of the total contract amount; Searle Trucking for trucking services equaling 1.29% of the total contract amount. The total WBE percentage is 5.29%; the goal is 5%. The subcontractor utilization statement further indicates that ICCI will be utilizing the following MBE subcontractors: Millennia Professional Services for layout and QC/QA services totaling 6.69% of the total contract amount; Kerry Brown for trucking services equaling 3.85% of th...