File #: 22-318    Version: 1 Name: Merle at Knoxville Culvert
Type: Contract Status: Approved
File created: 9/12/2022 In control: City Council
On agenda: 9/27/2022 Final action: 9/27/2022
Title: Communication from the City Manager and Director of Public Works with a Request for the Following: A. ACCEPT the LOW BID from STARK EXCAVATING, INC., in the Amount of $1,265,139.00, and APPROVE a CONTRACT for Culvert Replacement Carrying the East Branch of Dry Run Creek Under MERLE LANE, with an Additional Authorization of $126,861.00 (10%) for Contingencies, for a Total Award of $1,392,000.00. (Council District 2) B. ADOPT an ORDINANCE Amending the City of Peoria 2022 BUDGET to Allocate $881,000.00 from the Stormwater Utility Fund Balance for the MERLE LANE CULVERT REPLACEMENT PROJECT.
Attachments: 1. Budget Amendment TMP-5788, 2. 22-318 Agreement_0001
Related files: 21-356
ACTION REQUESTED:
Title
Communication from the City Manager and Director of Public Works with a Request for the Following:

A. ACCEPT the LOW BID from STARK EXCAVATING, INC., in the Amount of $1,265,139.00, and APPROVE a CONTRACT for Culvert Replacement Carrying the East Branch of Dry Run Creek Under MERLE LANE, with an Additional Authorization of $126,861.00 (10%) for Contingencies, for a Total Award of $1,392,000.00. (Council District 2)

B. ADOPT an ORDINANCE Amending the City of Peoria 2022 BUDGET to Allocate $881,000.00 from the Stormwater Utility Fund Balance for the MERLE LANE CULVERT REPLACEMENT PROJECT.

Body
BACKGROUND: The project consists of a new culvert to replace a deteriorated corrugated metal pipe culvert carrying the East Branch of Dry Run Creek under Merle Lane just west of Knoxville Avenue. The project includes stabilization of the channel at the upstream and downstream ends of the new culvert, rerouting of an existing 24" sanitary sewer within the stream channel to allow for the construction of the new drainage structure, and restoration of the area with trees, shrubs on grass.

The contract was advertised on August 8th and 9th and bids were opened on September 7th with the following bids received:
Contractor Bid Amount
Otto Baum $1,618,198
Stark Excavating $1,265,139
Engineer's Estimate $1,046,342

Midwest Engineers prepared the bidding and contract documents.

The work will be completed based on bid unit prices. Public Works staff is recommending adding a 10 percent contingency to account for unknown conditions that are encountered as the work is performed.

Stark Excavating has successfully performed work for Peoria in the past. Stark Excavating proposes to use JD Traffic (WBE), Central Landscaping (WBE), Kerri Brown Trucking (MBE), and Kadilex Construction (MBE). The M/WBE work to be subcontracted amounts to 3.5% (10% goal) for MBE and 2.4% (5% goal) for WBE of the contract bid. Stark completed the Waiver Reque...